Owners Eneco and Econcern accomplish high turbine availability and energy yield
12 February 2009
Princess Amalia Wind Farm officially opened
04 June 2008
The last film of the building process.
04 June 2008
Ready:
Activity:
05-2007
Foundations
05-2007
Offshore transformator
station
07-2007
150 kV export cable
09-2007
22 kV cables
04-2008
Turbines
06-2008
Windfarm operational