Building process
| When: Until May 2007 |
Participant: Van Oord |
The installation of the foundations and transition pieces. Foundations measuring 54 metres, a diameter of 4 metres and 320 tons in weight are sunk into the sea-floor. The transition pieces weighing 115-tons are placed on the foundations using the Jumping Jack. |
|
| When: May 2007 |
Participants: Van Oord, Bladt |
The transformer station, 520 tons in weight, is being manufactured by Bladt in Denmark and will be transported to the Netherlands by sea. Installation of transformerstation by Van Oord. |
|
| When: May/September 2007 |
Participants: ABB, Van Oord |
Installation of 22-kV sea cables for the connection of the turbines with the high-voltage substation and 150-kV deep sea cable measuring 23 km that connects the substation with the shore. |
|
| When: May/November 2007 |
Participant: Vestas |
Production and installation of turbines. |
|
| When: July 2007 |
Participant: Van Oord |
Installation of 150-kV sea cables. |
|
| When: July 2007 |
Participant: ABB |
Production of all the equipment related to the transport and distribution of generated power. The main components for the offshore station: 150 kV and 22 kV gas-isolated switches, 140 MVA transformer and security and control equipment. |
|
| When: March 2008 |
|
| Wind farm operational. | |
| When: 2008 |
Participant: ENECO |
| Monitoring data. | |